A new-build 13,000m2 hospital spread over three floors.
The mechanical installation services involved the extension of heating and chilled water from an existing energy centre to serve ceiling mounted radiant heating and four-pipe fan coils units. Air handling units and associated ductwork distribution systems serve all areas of the building.
Hot water generation plant and hot & cold water distribution services, including the supply and installation of sanitaryware and above ground drainage, were also included in Airedale's work.
All service routes through the circulation corridors were pre-fabricated off site and delivered on modules, which were integrated with the structure, while ervices outside the corridors were installed conventionally.
The electrical services involved the installation of a modular wiring system throughout the whole building, including an L1 analogue addressable fire alarm system compliant to BS5739, while lighting used ceiling-mounted recessed luminaires
CONTRACT PERIOD: 90 WEEKS